Monday, July 14, 2014

HURRY UP AND...WAIT

Over the fourth of July we worked our butts off to get the insulation and PEX tubing installed so our concrete guy could come poor the slab, BUT he got tied up and couldn't come.  The slab, which is also our finished floor, can not be poured if there is a chance of rain, SO given the forecast he may not return for an additional 4 days.  This leaves us at a total stand still.  Right away we took advantage of the down time and got rid of ALL the garbage, did yard work and shopped for tile.  We found amazing porcelain tile that looks like weathered wood for the upstairs bathroom floor (at Dalene Flooring Outlet store in Hartford, CT)  and glass tiles for the shower surround (from good ol' CL!)  Both at a steal.